本文已被:浏览 820次 下载 314次
投稿时间:2020-03-04
投稿时间:2020-03-04
中文摘要: 探讨了核电站中1 000 kV送出升压站可行的设计方案。对1 000 kV 送出的一次升压和二次升压方案进行了技术经济比较研究,结果表明1 000 kV二次升压方案更适合核电站。该研究为我国后续核电站的1 000 kV送出升压站的设计提供了参考和借鉴。
Abstract:In order to discuss the feasible design scheme of 1 000 kV outgoing booster switchgear in nuclear power plant,this paper discusses the technical and economic comparison between the one-step and two-step boosting schemes of 1 000 kV outgoing booster switchgear,and draws the conclusion that the 1 000 kV two-step boosting scheme is more suitable for nuclear power plant from the technical and economic aspects,which provides reference for the design of 1 000 kV outgoing booster switchgear in China's subsequent nuclear power plants.
文章编号:20203007 中图分类号:TM623 文献标志码:
基金项目:
引用文本:
邱天明,马杰.福建漳州核电厂一期1 000 kV送出升压站设计方案研究[J].上海电力大学学报,2020,36(3):240-244.
QIU Tianming,MA Jie.Research on the Design Scheme of 1 000 kV Transmission Booster Switchgear for Fujian Zhangzhou Nuclear Power Plant Phase One[J].Journal of Shanghai University of Electric Power,2020,36(3):240-244.
邱天明,马杰.福建漳州核电厂一期1 000 kV送出升压站设计方案研究[J].上海电力大学学报,2020,36(3):240-244.
QIU Tianming,MA Jie.Research on the Design Scheme of 1 000 kV Transmission Booster Switchgear for Fujian Zhangzhou Nuclear Power Plant Phase One[J].Journal of Shanghai University of Electric Power,2020,36(3):240-244.