火电厂主辅机布局新方案
New Layout Scheme of Coal Fuel Power Plants Main Block
Abstract
Image-text
References
Similar literature
本文已被:浏览 1072次   下载 792
    
中文摘要: 通过对火力发电厂主辅机布置方案的优化,将煤仓间与锅炉进行合并,将除氧器布置于皮带层内,取消了除氧间,并缩短了汽机房和锅炉房之间的距离,以节省空间和昂贵的管材用量,从而减小了投资.另外,汽机房采用了钢网架屋顶结构,检修设备采用门式起重机,缩短了施工工期,并达到了美化汽机房外观的效果.
中文关键词: 火电厂  主辅机  汽轮机  除氧间
Abstract:After optimizing the layout scheme of fossil fuel power main block plants,bunker bay is combined with boiler,deaerator is installed over the belt conveyor floor. Deaerator house is canceled,so it reduces the distance between the turbine house and boiler house,so that the space and expensive piping material cost is reduced. In addition,steel net frame structure is adopted on the roof of the turbine house,and the door type of crane is adopted on the maintenance device,so that the time of erection is eliminated and the surface of turbine house is beautified.
文章编号:20110310     中图分类号:    文献标志码:
基金项目:上海市自然科学基金(07ZR14042)
Author NameAffiliationE-mail
SU Zhi-hua  su8s1856@126. com. 
CUI Fen   
YUAN Zhi-xian   
Author NameAffiliationE-mail
SU Zhi-hua  su8s1856@126. com. 
CUI Fen   
YUAN Zhi-xian   
Reference text:


###
DOI:
Journal of ShangHai University of Electric Power :2011,(3):-
View/Comment     Archive    Advanced search     HTML
←Previous   |   Next→
Abstract
Image-text
References
Similar literature
本文已被:浏览次   下载
    
中文摘要:
中文关键词:
Abstract:
keywords:
文章编号:20110310     中图分类号:    文献标志码:
基金项目:
Reference text: